Tender works programme
The Code of Estimating Practice, seventh edition, published by the Chartered Institute of Building (CIOB) in 2009 suggests that the term ‘tender works programme’, refers to:
A programme based on a global strategy for the project resulting from the information available at tender stage. It should not be relied on for construction purposes but may legitimately be the basis for the construction master programme. Its purpose is to demonstrate that the contractor intends to comply with the date constraints listed in the tender documents and, where a contract period is not specified, it will indicate the completion date and hence, the duration over which the time-related site costs must be included in the tender. It should be prepared as a critical path network in order to identify critical work activities and delivery dates of client supplied information, goods and materials. It is not uncommon for the tender documents to require the tender works programme to be submitted with the tender. |
NB, This should not be confused with the 'tender preparation programme', which is the, ‘…resourced activity schedule outlining (the) programme for the preparation and submission of (the) tender’.
--CIOB
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
- Accepted programme.
- Activity schedule.
- Chartered Institute of Building.
- Code of Estimating Practice.
- Contract documents.
- Contractor's master programme.
- Cost plans for construction projects.
- Design programme.
- Information release schedule.
- Milestones.
- Programme.
- Programme consultant.
- Programme for building design and construction.
- Project crashing.
- Scheduling construction activities.
- Short period programme.
- Tender documents.
- Tender.
- Time-location chart.
Featured articles and news
From Chaucer to Fawlty Towers.
Electrotechnical excellence, now open for entries.
Net zero electricity grids BSRIA guide NZG 5/2024
Outlining the changes needed to transition to net zero.
CIOB Global Student Challenge 2024
Universitas Indonesia wins for second year running.
New project and cultural district described in detail.
The nature of EPCs, crticism and inaccuracies.
History, issues and redesign.
From waste recycling to energy performance the hierchy.
An introduction to WERCS and WEEE responsibilities
Dealing with 2 million tonnes of waste equipment a year.
Global BACS Market: analytics and optimisation
A BSRIA glance at building automation and control systems.
What it is and how to use it.
Types of insulating plaster by binder and insulant.
Investors in People: CIOB achieves gold
Reflecting a commitment to employees and members.
Scratching beneath the surface; a guide to selection.
ECA 2024 Apprentice of the Year Award
Entries open for submission until May 31.
UK gov apprenticeship funding from April 2024
Brief summary the policy paper updated in March.